Project Status

The project is making rapid progress at Demwe Lower site.

Demwe Lower

  • Topographical survey, Property survey and Construction Material Survey have been completed.
  • Geological Mapping, Geophysical investigation and Sub Surface Investigations including Drilling & Drifting completed.
  • Socio-economic Study, all season base line data collection and study completed.
  • Defence clearance obtained from Ministry of Defence.
  • Detailed Project Report (DPR) has been concurred by the CEA.
  • Environmental Clearance has been accorded by Ministry of Environment & Forests.
  • The project has been taken up to be developed as CDM project and for registration at CDM Executive Board of UNFCCC. The Project Design Document (PDD) is under development.
  • The Project has been taken up to be developed as CDM Project and for registration at CDM Executive Board of UNFCCC. The PDD Development has been completed.
  • Prior CDM intimation to UNFCCC and National CDM Authority (NCDMA) has been provided in December, 2010
  • Designated Operational Entity (DOE) has been recruited for Validation of the Project in December, 2010.
  • The PDD of the Project has been webhosted in the UNFCCC website by the appointed DOE, for the period of 31st May to 29th June 2011 for Global Stakeholders' Consultation.
  • Project has been cleared from the Wildlife angle by the Standing Committee of NBWL, MOEF on 11th Feb 2012.
  • "In Principle" Forest clearance ( Stage-I ) obtained from Ministry of Environment & Forests on 1st March, 2012.
  • Project has been accorded Forest Clearance by Ministry of Environment & Forests on 3rd May, 2013.